Workfront request conversion can leave protected project fields blank

Test Workfront request-to-project field transfer with the actual converting role before intake data goes missing.

November 17, 2026

The project can start with an approved go-live date on the request and an empty go-live date on the converted project. A recent Workfront community report describes this when destination form fields are visible to everyone but editable only by admins. Another participant could not reproduce it, so treat it as a role-and-form configuration risk to test, not a universal product defect.

Reproduce the handoff as the converter

Create a disposable request with a target date and funding ID. Convert it as the same non-admin role used by the PMO, then read both values on the new project. Repeat with direct sign-in and an admin 'Log in as' session; the community thread shows these paths gave different observations. Record the form IDs, field IDs, template, access level and conversion choice with the result.

Check the documented transfer contract

Adobe's transfer guide requires the form to support the destination object and to be selected during conversion. Confirm the same fields exist on both sides before treating a blank destination as a permission issue. Adobe's conversion overview describes what carries over; the admin-only edit rule deserves a separate acceptance test.

Put a reconciliation at the project boundary

Until this is resolved in your configuration, compare the handful of decision fields on request and project immediately after conversion. Route any mismatch to a named administrator with the request and project IDs. Keep the original request linked so the evidence is recoverable; do not ask a non-admin to work around the access policy by granting broader edit rights.

Adovo’s view

A conversion is a data contract, not a button click. The PMO should be able to prove which approved facts crossed from intake into delivery, under the permissions used in real work. If that proof fails, stop the project handoff before someone builds a plan from empty fields.

Continue exploring

Adobe Experience Cloud

Adobe WorkfrontIntegrations

Workfront API access has a deadline beyond the login screen

Inventory custom Workfront OAuth clients before the February 2027 retirement; test their replacement identity and permissions.

Read more

Adobe Experience Cloud

Adobe WorkfrontProofing

Workfront Proof replies can miss the reviewer who needs them

Design a clear owner for proof comment follow-up when per-thread subscriptions are unavailable.

Read more

Adobe Experience Cloud

Adobe WorkfrontProof reporting

Workfront proof reports need the approver’s actual decision interval

Define which Workfront proof events support a per-approver open-to-decision report across versions.